MTCC report progress of road development project at Dhuvaafaru

Popular

Road development at R. Dhuvaafaru | Photo: MTCC

Maldives Transport and Contracting Company (MTCC) confirm notable progress of road development project at Raa atoll Dhuvaafaru.

As such, MTCC on Wednesday confirms the project was well underway with 67% progress.

Overall the “ABC works for 12 major roads, which cover an area of 3,312.23” square meters were completed on 14 July 2020.

Meanwhile the scope of work under project involves sidewalk installation in a 6,813 square meter area.

Additionally the project involves installation of road drainage, lighting and signage.

MTCC reports project total at an estimation of MVR47.04 million.

Earlier, Maldives government assigned the project to MTCC on 22 May 2019.

MTCC reports mobilization of the project on 12 June 2019.