MTCC carries forward football ground project in Hoarafushi

Popular

Football ground development at Hoarafushi | Photo: MTCC

Maldives Transport and Contracting Company (MTCC) reports progress of football ground development at Haa Alif atoll Hoarafushi.

As per the contractor, the project entails ground sub-base preparation for the pitch.

Moreover, MTCC notes kerb stone laying and drainage gutter top casting were ongoing.

Additionally, the contractor was progressing with sub-base fill leveling along with compaction works.

MTCC comments the project involves site clearance and compaction in an area of 8,103 square meters. The area also requires excavation before the grounds are leveled.

Furthermore, MTCC will install a soaking pit in the football pitch.

The contractor estimates project value at MVR2.53 million, with Ministry of Youth, Sports and Community Empowerment awarding the works.

Earlier, during their quarterly report MTCC confirms completion of several projects across Maldives.

Moreover, it notes work in at least over 70 different development projects in parts of the country.