Landhoo harbor development project underway

Popular

Maldives Transport and Contracting Company (MTCC) confirms work on design and build of Noonu atoll Landhoo harbor underway.

Moreover, MTCC confirms an overall project progress of 26%, with dredging works at ongoing status.

According to the contractor, dredging works are currently at 30% of project progress.

Furthermore the project entails sidewalks spanning 6,813.08 square meters, along with a 25,513 square meter carriageway development.

Additionally, installation of road lights and markings fall under the project scope as well.

Meanwhile MTCC estimate project value at MVR35.60 million.