Maldives Transport and Contracting Company (MTCC) reports mobilizing their full team with machinery to Shaviyani atoll Feydhoo harbor project site.

Moreover, the contractor confirms the project team with machinery arrived on 05 January 2021.

Feydhoo harbor development project estimates a total of MVR33.1 million, inclusive of all project components.

Furthermore the project entails, dredging and excavation operations spanning 27,500 cubic meters.

Other components of it include construction of a 378 meter breakwater along with a 90 meter revetment. Additionally, MTCC will construct a 276 meter quay-wall at the harbor.

The contractor will install 1,380 square meters of paved area along with installation of street and navigation lights.