Fehendhoo harbor project nears completion

Popular

Photo: MTCC

Maldives Transport and Contracting Company (MTCC) reports Baa atoll Fehendhoo harbor project is nearing completion.

Moreover, the contractor notes work on design and build of the harbor is well underway with overall 75% project progress.

MTCC further attests completion of quay wall construction.

Scope of work for the project includes new harbor’s basin dredging which spans 18,500 cubic meters. Moreover, new entrance channel dredging works which span 25,000 cubic meters.

Furthermore, MTCC will construct 130 meters of breakwater and 282 meters of revetment.

Additionally, installation of navigation and streetlights are part of the project.

MTCC will also install a pavement area spanning 558 square meters.

Meanwhile, the project contractor reports the total project value at MVR45.1 million.