Maduvvari South Harbor project underway, 45% progress

Popular

Photo: MTCC

Maldives Transport and Contracting Company (MTCC) confirms on Thursday, progress of Raa atoll Maduvvari south harbor project.

Moreover, MTCC attests overall 45% project progress on work on design and build of the harbor development.

The harbor development scheme consists of dredging 7,280 cubic meters from channel, dredging 65,520 cubic meters from harbor basin.

Furthermore, the project entails breakwater construction of 411 meters and quay wall construction spanning 566 meters.

Additional components include revetment of 135 meters along with installation of 2,825 square meters of pavement.

MTCC will also install both navigation and streetlights as part of the project scheme.