Guraidhoo harbor project observes 40% progress

Popular

Photo: MTCC

Maldives Transport and Contracting Company (MTCC) on Sunday, 28 March 2021, reveals project progress of Thaa atoll Guraidhoo harbor development.

Moreover, the contractor affirms work on design and build of the island’s harbor observes overall 40% progress.

MTCC announces completion of installing precast concrete blocks for the quay wall construction segment of the project.

Furthermore, the project involves dredging and excavation operations of 24,485 cubic meters.

Additional components include construction of a 325-meter breakwater, 185 meter quay wall and a 22-meter revetment.

MTCC will also install a pavement spanning 1,875 square meters while the contractor reports project value at MVR46.01 million.