Foakaidhoo project site receives first shipment of rock boulders

Popular

MTCC delivers rock boulder shipment to project site | Photo: MTCC

Maldives Transport and Contracting Company (MTCC) reports delivering first shipment of rock boulders for Shaviyani atoll Foakaidhoo’s harbor project.

Moreover, the contractor affirms delivery of the shipment for the island’s breakwater construction, on 24 March 2021.

Meanwhile, dredging works for the new harbor basin is ongoing with 58% work completion.

The project consists of new harbor basin dredging spanning 39,995 cubic meters, and dredging of existing harbor basin for another 1,800 cubic meters.

Furthermore, additional components include construction of a 507-meter breakwater, 100-meter revetment and a 464-meter quay wall.

Additionally, MTCC will install a 2,320 square meter pavement, along with installation of navigation and streetlights.

MTCC reports project value at a total of MVR52.7 million.