MTCC inches to completion of Eydhafushi road construction project

Popular

Photo: MTCC

Maldives Transport and Contracting Company (MTCC) on Wednesday, 09 June 2021, stated they were nearing completion of Baa atoll Eydhafushi road construction project.

According to the project contractor, the project has observed an overall 96% completion while the contractor was currently installing stormwater pump station, which has progressed 98% as well.

Moreover, MTCC reports the project consists of the construction of stormwater lift stations, along with asphalt wearing course and installation of street lights.

Additionally, MTCC will install road markings along with speed breakers as well.

The developer estimates project value at a total of MVR34.42 million.