MTCC reports 68% progress of Hulhudhoo harbor project

Photo: MTCC

Maldives Transport and Contracting Company (MTCC) has reported on the recent developments of Addu City Hulhudhoo harbor project.

Moreover, the contractor affirmed that the design and build of the harbor has observed 68% completion. Furthermore, MTCC confirms on the installation of precast concrete blocks and concrete works for the quay wall currently at ongoing status.

Hulhudhoo harbor development project involves dredging and excavation operations spanning 88,623 cubic meters along with structure developments.

The structures include the construction of a breakwater, revetment and quay wall measuring 114 meters, 624 meters and 742 meters respectively.

Furthermore, the project also includes construction of a pavement measuring 2,250 square meters along with the installation of street lights.

Meanwhile, MTCC confirms the project value is a total of MVR65.1 million.