MTCC commences quay wall construction of Miladhoo harbor project

Maldives Transport and Contracting Company (MTCC) confirms commencing initial stage of quay wall construction under Noonu atoll Miladhoo harbor project.

According to the project contractor, it has commenced installation of precast concrete blocks required for the construction of the quay wall structure. Moreover, the contractor had reported commencement date as 27 November, Saturday.

Project scope under the Miladhoo harbor development includes dredging and excavation operations spanning 37,222 cubic meters along with construction of a 209 meter breakwater, 152 meter revetment and a 286-meter quay wall.

In addition to this, MTCC will be developing a paved area in the harbor site spanning 1,430 square-meters along with the installation of navigation and street lights.

Meanwhile, the contractor affirmed the project was valued at a total of MVR42.1 million.