Foakaidhoo harbor development project over 60% progress

Popular

Work on design and build of Shaviyani atoll Foakaidhoo harbor development project is underway with an overall progress of 62%.

Meanwhile, the contractor reported that the fourth shipment of precast concrete blocks required for the quay wall construction had been delivered to project site on 15 April 2022.

Project scope involves dredging operations of 45,795 cubic meters of sand mass along with the construction of a quay wall stretching 464 meters.

In addition to this, other structural development components of the project include a 507 meters breakwater, installation of a 2,320 square meters harbor pavement along with the installation of street lights and navigational lights.

Furthermore, MTCC attests that the project total is valued at MVR64.6 million.