MTCC completes quay-wall block installation

Popular

Maldives Transport and Contracting Company (MTCC) has completed the installation of the blocks for the quay wall in Dhaal atoll Meedhoo’s harbor.

Under the harbor construction project the concrete works of the quay wall is currently at ongoing status.

According to the project contractor, the harbor development project consists of dredging and excavation operations, construction of a 373 meters breakwater, 35 meters revetment and an 11 meters by 11 meters ramp.

The quay wall structure, which is currently being executed will measure 294 meters in length upon completion.

Additional components of the project entail installation of a 1,470 square-meter pavement along with installation of navigational and harbor lights.

Meanwhile, MTCC has reported that the project total is valued at MVR34.07 million.