N. Velidhoo Boat Beaching Area Project observes over 50% completion

Popular

Boat Beaching Area Project underway at N. Velidhoo (Photo / MTCC)

Maldives Transport and Contracting Company (MTCC) has completed over half of the Boat Beaching Area Project currently underway in Noonu Atoll Velidhoo.

The company revealed they have completed 56% of the total work on the project. They further said levelling of reclaimed area is currently underway, with 86% completion.

Under the project, an area of 1.5 hectares will be dredged. 138,247 acres of the reclaimed area will be leveled and 214 acres of rivetment will be installed. In addition, MTCC will construct 100 metres of breakwater adjacent to the reclaimed area.

The project was awarded to the State-Owned Enterprises for MVR 19.4 million.