MTCC provides update on shore protection projects in Kendhoo and Nellaidhoo

Popular

MTCC provided update on B. Kendhoo Shore Protection Project (Photo / MTCC)

Maldives Transport and Contracting Company (MTCC) on Sunday provided the latest update on the progress of the Shore Protection Projects in Haa Dhaal Atoll Nellaidhoo and Baa Atoll Kendhoo.

Commenting on B. Kendhoo project, MTCC revealed that the swimming area dredging works have been completed. Breakwater construction works are currently ongoing at the site, with 65% completion.

Scope of works for the project include dredging operations of swimming track, construction of a 803m breakwater and a 80m rock boulder revetment. The value of the project is MVR 39.9 million.

According to MTCC, final shipment of rock boulders required for Hdh. Nellaidhoo Shore Protection project has been delivered to the project site on 25th September 2022. Revetment building works are currently ongoing at the site, with 66% completion.

Scope of works include, swimming area dredging works and construction of a 870m rock boulder revetment. MTCC revealed that the value of the project is MVR 19.8 million.