News
Land reclamation works in HA. Dhidhoo are progressing steadily as planned, with 41 hectares reclaimed so far, accounting for 36.61 per cent of the overall project completion.The works are being carrie...
Mohamed Hilmy
25 January 2026, 00:00
Land reclamation works in HA. Dhidhoo are progressing steadily as planned, with 41 hectares reclaimed so far, accounting for 36.61 per cent of the overall project completion.
The works are being carried out by Leiv Eiriksson, a trailing suction hopper dredger with a capacity of 46,000 cubic metres. The vessel is currently undertaking dredging and reclamation operations to ensure the project remains on schedule.
The reclamation project is expected to significantly contribute to the development of Dhidhoo, particularly in supporting airport expansion, housing initiatives, and the provision of essential community infrastructure.
Maldives Airports Company Limited (MACL) commenced the land reclamation works in Dhidhoo on 5 January 2026. Once completed, the project is expected to enhance connectivity and improve living standards for residents in the area.
No comments yet. Be the first to comment!
News
Maldivian Expands Domestic Network with Scheduled Flights to Kudahuvadhoo
13 Sep 2026
News
BML to Offer All New Personal Accounts and Financing Under Islamic Banking Principles
13 Sep 2026
News
BML Introduces Daily Limits for International Transactions on MVR Cards
12 Sep 2026
News
Qatar Airways to Increase Maldives Flights to Three Daily This Winter
12 Sep 2026