News
Land reclamation works for Hulhumalé Phase 3 have reached 50 percent completion, reflecting steady progress in the ongoing urban expansion project. A total of 31.5 hectares out of the planned 63 he...
Mohamed Hilmy
16 December 2025, 00:00
Land reclamation works for Hulhumalé Phase 3 have reached 50 percent completion, reflecting steady progress in the ongoing urban expansion project. A total of 31.5 hectares out of the planned 63 hectares has now been reclaimed.
The project is
currently being carried out with two dredgers, Prins der Nederlanden and
Oranje, each with a dredging capacity of 22,000 cubic metres, actively
operating at the site to maintain the pace of reclamation.
The Phase 3
reclamation works are being undertaken by Maldives Airports Company Limited
(MACL), which commenced the project on 10 November 2025. Upon completion, the
reclaimed area is expected to support future housing and infrastructure
development, contributing to long-term urban planning efforts and easing
development pressure in the Greater Malé region.
No comments yet. Be the first to comment!
Features
Are Dates the Most Powerful Food of Ramadan?
24 Feb 2026
News
STO Maintains Affordable Orange Prices as Market Prices Rise
24 Feb 2026
News
Fifth Day of Ramadan Sees Watermelon as Top Cleared Item at MPL
24 Feb 2026
News
Allied Marks 41 Years with Limited 25% Discount on Motorcycle Comprehensive Insurance
24 Feb 2026